What is a “construction contract” and why does it matter?

What is a “construction contract” and why does it matter?

When embarking on construction work, understanding at the outset whether your contract is determined a “construction contract” is vital. This can help avoid unexpected payment issues and potential disputes arising further down the line.

A “construction contract” is not simply a building contract under the Housing Grants, Construction and Regeneration Act 1996  (the ‘Act’) – the definition is wide-reaching with several important terms implied which can significantly impact a construction project.

What is a “construction contract”?

The Act defines a “construction contract” as an agreement for the carrying out, arranging, or  providing labour for construction operations.

Construction operations are widely defined under the Act and can include:

  • building
  • alterations
  • repair
  • maintenance
  • extension and demolition works
  • civil engineering works
  • installing building systems
  • site preparation
  • scaffolding
  • landscaping; and
  • painting/decorating.

They can also include contracts for architectural, design, surveying work and certain contracts for professional advice relating to construction works and some development agreements that might be dealt with in real estate transactions.

There are specific exclusions which take the relevant contract outside of the Act, such as certain finance agreements, planning agreements and contracts with residential occupiers.

Implied terms in a “construction contract”

If under the Act your contract is a “construction contract” then important terms can be implied even when not expressly written into the contract:

  1. Payment

The Act provides that a party is entitled to payment by instalments, stage or periodic payments unless:

  • The contract specifies that the duration of the work is to be less than 45 days; or
  • It is agreed between the parties that the duration of the work is estimated to be less than 45 days.

The Act also requires inclusion of a payment procedure which, amongst other things, requires  a “due date” and a “final date” for payment and a requirement for a “pay less notice” if a party does not consider that a payment is due.

Where a construction contract does include the required payment provisions or they are not compliant with the Act, they are implied.

You could therefore find payment provisions applying which aren’t expressly set out in your contract.

  1. Adjudication

If a construction contract does not include an adjudication procedure, then this will be implied. Adjudication is a quick form of dispute resolution which can be used to decide disagreements which arise during a construction project, without the need to go to court or arbitration. Where adjudication provisions are included but are not compliant with the Act, for contracts in England and Wales the adjudication procedure is replaced with the compliant procedure. The Act’s adjudication procedure could therefore be unexpectedly applicable to your contract.

Why consider this at the outset?

Understanding whether the Act applies to your contract from the outset can ensure your contracts are adequately structured and negotiated to avoid unexpected and unwelcome payment issues and potential disputes arising as your project progresses.